📕 Setup - Resource Rates
Last updated: September 23, 2026
Overview
Resource Rates can be used to track and measure labor cost. Resource Rates are associated with Resources via the User Edit screen.
Note: Labor cost totals will be displayed on the main dispatch screen during the job.
Prerequisites & Preparation
Required Permissions: Resource Manager or Administrator
Step-by-Step Configuration
Navigate to the Menu: Go to Setup > Resource Rates.
Initiate Creation: Click Add New in the upper right corner of the Resource Rates bar.
Enter Details:
Labor Rate Description/Name: Enter a name for the rate.
Rate (Hourly): Enter the hourly rate.
Note: This is typically the fully burdened rate for the pay scale.
Define Attributes: N/A
Save & Finalize: Click Save.
Troubleshooting: Labor Costs Not Displaying on a Dispatch
If you aren't able to see labor costs associated with a Dispatch, make sure the Resource or Technician who was dispatched has a Resource Rate associated with their User Profile. This setting is only available to L2L Administrators.
Steps to check/fix:
Navigate to the User: Go to Setup > Users, then locate the Resource (e.g., "Joe" or "Joan Doe").
Open the Profile: Click on the username to open the Edit User page.
Locate the Field: Find the dropdown labeled Resource Rate.
Assign the Rate: Select the option that corresponds to this Resource or Technician.