Target Quantity is a production value that can be enabled in Production > Settings that provides a benchmark for productivity based on the ideal performance a Line can achieve creating a particular product.
Target is different from Demand in that while Demand represents the planned Production, Target represents what is possible given current circumstance. As such, they will rarely have equivalent values.
The pitch Target Quantity is automatically set by L2L once the pitch is the current pitch (the current date and time fall within the scope of the pitch), and is based on several properties of the pitch:
- Active/Inactive
- Target is only set for Active pitches, as this represents a pitch where production is planned to be performed
- Downtime
- Any downtime experienced within a pitch, automatically calculated by L2L from Dispatches against the Line with a "Down (red)" Impact to Production, is subtracted from the available production minutes as part of the pitch Target Quantity calculation
- ex) For 15 minutes of downtime in a 60 minute pitch, a duration of 45 minutes (60 - 15 min) will be used for the Target calculation
- Any downtime experienced within a pitch, automatically calculated by L2L from Dispatches against the Line with a "Down (red)" Impact to Production, is subtracted from the available production minutes as part of the pitch Target Quantity calculation
- Operator Count
- This is specified on the pitch either through the Operator Count field on the pitch edit modal or is derived by L2L from the Users checked into the Line during the pitch
- Actual Product
- The Actual Product for a pitch is defined either by the Product field on the pitch edit modal or is automatically pulled from the Current Order widget in the Operator Portal when the pitch is saved
- Apply Planning Rate to Target: the value for Cycle Time in the Target calculation will vary according to whether this setting is toggled on in Production > Settings
- Apply Planning Rate to Target not enabled (FALSE)
- Target = {[Planned Production Time (min) β Production Downtime (min)]*60 (s/min)} / [Ideal Cycle Time (s)]
- Ideal Cycle Time defined by
- Product Order Group Pitch Cycle Time
- OR Ideal Cycle Time in Line Cycle Time table by
- Line
- Product: Actual Product recorded on pitch
- OR Line Cycle Time in Line Cycle Time table by
- Line
- Product: Actual Product recorded on pitch
- Operator Count: actual Operator Count on pitch
- Cycle Time for the largest Operator Count that is less than the pitch Planned Operator Count if specific count not identified
- OR only Cycle Time in the Cycle Times per Operator Count table will be used (when only a single Operator Count and Cycle Time is listed)
- OR Line Cycle Time in Line Cycle Time table by
- Line
- Default Product
- Operator Count: actual Operator Count on pitch
- Cycle Time for the largest Operator Count that is less than the pitch Planned Operator Count if specific count not identified
- OR only Cycle Time in the Cycle Times per Operator Count table will be used (when only a single Operator Count and Cycle Time is listed)
- Ideal Cycle Time defined by
- Target = {[Planned Production Time (min) β Production Downtime (min)]*60 (s/min)} / [Ideal Cycle Time (s)]
- Apply Planning Rate to Target enabled (TRUE)
- Target = {[Planned Production Time (min) β Production Downtime (min)]*60 (s/min)} / [Cycle Time (s)]
- Cycle Time defined by
- Product Order Group Pitch Cycle Time
- OR Build Sequence Cycle Time for active Build Sequence on pitch
- OR Line Cycle Time in Line Cycle Time table by
- Line
- Product: Actual Product recorded on pitch
- Operator Count: actual Operator Count on pitch
- Cycle Time for the largest Operator Count that is less than the pitch Planned Operator Count if specific count not identified
- OR only Cycle Time in the Cycle Times per Operator Count table will be used (when only a single Operator Count and Cycle Time is listed)
- Planning Rate: if defined for the Line and Product combination
- Cycle Time = Cycle Time by Line, Product (s) / [Planning Rate % /100]
- OR Line Cycle Time in Line Cycle Time table by
- Line
- Default Product
- Operator Count: actual Operator Count on pitch
- Cycle Time for the largest Operator Count that is less than the pitch Planned Operator Count if specific count not identified
- OR only Cycle Time in the Cycle Times per Operator Count table will be used (when only a single Operator Count and Cycle Time is listed)
- Planning Rate: if defined for the Line and Product combination
- Cycle Time = Cycle Time by Line, Product (s) / [Planning Rate % /100]
- Cycle Time defined by
- Target = {[Planned Production Time (min) β Production Downtime (min)]*60 (s/min)} / [Cycle Time (s)]
- Missing values within the Line Cycle Tables can result in blank Target Quantity values on the Operator Portal
- Apply Planning Rate to Target not enabled (FALSE)