You can attach reference materials to product orders and their build sequences so operators have what they need, and review standard work that was completed during a run.

Attachments vs. Documents

Attachments

Documents

What they are

Files that aren't stored in Leading2Lean as documents

Documents from L2L's Documents module

Examples

Pictures of product labels, raw material containers

Product specification sheets, visual standard documents

Where to add them

Edit the product order

Edit the product order or a build sequence

Adding attachments to a product order

  1. From Production > Product Orders, open the order and click Edit.

  2. In Attachments, add the files you need.

Order-level vs. sequence-level documents

Documents can be connected at two levels:

  • Order-level documents: From the Product Order screen, click Edit, then select the documents from the Documents drop-down.

  • Sequence-level documents: When adding or editing a build sequence, add documents related to that specific sequence. These are supplementary to the order-level documents.

After saving, the attached documents are listed at the bottom of the Product Order screen, showing whether each one is associated with the order or with a particular sequence.

Viewing completed Production Standard Work

On the Product Order screen, Production Standard Work displays any standard work documents that were completed while the order was in process on the Operator Portal. Use it to review standard work after a run.