Schedules with no resources
The issue I am having is when we lose a team member and make that individual's username "inactive", it removes that person's name from all schedules and continues to launch them. Could we have a report added so that we can run run a report for schedules with no assigned resources? Or maybe when a user is "inactivated", a report is generated and sent to the site admins listing out what schedules that resource was removed from?
-
Official comment
Hello Nolan,
I am happy to create a new Feature Request for you. In the meantime, here's a way to get the information you're looking for.
You can temporarily re-activate the Resource and see all the Schedules and Dispatches to which that Resource has been assigned.
After temporarily reactivating the Resource, you can also run a Resource Time Pareto Report. From that initial report, click on Resource(s), and then look at the History Detail Report.
These should provide the information you want. If you have any questions about either of these approaches, please let us know.
Thank you, Nolan.