You may be wondering how to go about rescheduling build sequences of a product order without having to edit each one manually. Well, there are two options in the UI currently.
1. If you are using the ekanban planner and your build sequences are allocated to one Area and Line, you can simply choose the 'Scheduling' button on that page and use the 'Start/End' fields to update the order dates.
2. If you do not have build sequences that are defined by one Area and Line, it gets a bit tricky. First, you'll want to make sure that your order has dependencies set up for the build sequences. Now, you'll want to use the Order Planner. From this screen, you can drag and drop one of the sequences to the desired date/time and the rest will follow.
3. The third option requires the use of the API as well as the knowledge from your team to build a script to handle the rescheduling. This script would then be able to filter through scheduled sequences and update the start and end dates.