The Record API for both Product Orders and Build Sequences have a field for 'Status'. The status is given to you as an integer value. Product orders represent a parent object where Build Sequences are children to the Product Order and represent the individual line level production steps required to build the parent order's product.
Both Product Orders and Build Sequence share a common set of statuses. The lists below are what each status integer value refers to.
Statuses
0 - New (This is the default status when importing product orders without defining a status on the spreadsheet.)
1 - Planning (This status can be used for the planning stage of your product order.)
2 - Scheduled (This status is used once you're ready to run your product order and will allow it to appear in the ekanban queue of the Operator Portal.)
3 - Ready to Build (This status gives some definition to product orders that are ready versus scheduled. Both statuses essentially do the same thing but give the operators more insight on what should be next.)
4 - Changeover/ Setup (This status is given for the interim time between product orders as you setup or change equipment to begin work on the next product.)
5 - Work in Progress (This status designates that the product order is currently being worked on.)
6 - On Hold (This status is given when your product order is placed on hold for a variety of reasons; out of materials, a different product order was more urgent, plant shutdown.)
7 - Completed (This status signifies that the product order is done.)
8 - Canceled (This status is used for any product orders that are no longer needed or removed.)
9 - Cleanup (This status is used for product orders that are in a clean-up state, before being completed)
Comments
0 comments
Please sign in to leave a comment.