Carrying Forward Past Due Pace

Last updated: June 19, 2026

Scenario: Line A has a demand of 500 parts for the week, but only 450 parts are produced. The pace at the end of the week is -50. Customer demand hasn't changed, so Line A must build 50 extra parts the next week. Fortunately, there are a few ways to carry the demand forward.